Philip Morris
C&I Close Out Report C&I Plan Number 78
Fields
- Type
- REPT, REPORT, OTHER
- FORM, FORM
- Master ID
- 2024794812/4813
Related Documents: - Site
- M45
- Litigation
- Stmn/Produced
- Named Person
- Ampey, D.
- Estes, B.
- Hall, D.
- Hartsell, C.
- Moore, A.
- Orms, D.
- Williams, W.
- Estes, B.
- Document File
- 2024794524/2024794872/Sp Operating Problems Worklife
- Issues Principles Nonconformances
- 2024794736/2024794871/T0913 0.080
- Issues Principles Nonconformances
- Area
- JENKINS,DEBBIE/OFFICE
- Date Loaded
- 31 Jan 1999
- UCSF Legacy ID
- cpu79e00
Document Images
, !f
/
.
PhiliConfidentiai
T~
: [Clo . -..
C&I Plan # 78 AOP CODE: N/A
Problem 1992 Union Contract consolidatedthe Forkiift/Checker and General Laborer
classiflcation. Some General Laborers are not trained to perform forklift and/or checker
assignments In various areas.
Start Date 9/18/92
Problem Soiving Determine training needs and develop training schedule so that we can abide by the
Ob eciive intent of the Union/Maria ement a reement
Team B. EstesD. Half. C. Hartseil, D. Orms, D. Am ey, A. Moore. W. Williams
'
Solutions and Date Will train sufficient numbers In each area to support lift truck assignments In
those
Implemented areas (Manpower General Laborers to be trained for Shipping). Once Implemented, all
Packing General Laborers will have been trained and two per shift per line will have
been trained InBiending and two Manpower Generat Laborers will have been trained
per shift for Shipping. In addition area checking training needs will have been
satisfied. Checker training has been completed: Shipping - 4/22&23/93, Warehouse
4/28&29/93. All lift assignment training is scheduled during the month of June (7-9, 14
16, and 21-23).
Measures of N/A
Effectiveness Befor
Measures of N/A
Effectiveness After
TQM's Impacted ~/A
Close Out Date 23-Jun-93
C&ICLOSE.XLS
Issue Date: 5/5/93