Philip Morris
A Case Study: Cost Implications for Hvac Commissioning
Fields
- Author
- Harmon, J.J.
- Seelen, J.
- Woods, J.E.
- Type
- SCRT, REPORT, SCIENTIFIC
- ABST, ABSTRACT
- BIBL, BIBLIOGRAPHY
- CHAR, CHART, GRAPH, TABLE, MAPS
- Area
- CENTRAL FILES/PRE-DB WAREHOUSE
- Document File
- 2021578674/2021578937/Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control
- Litigation
- Ppla/Produced
- Characteristic
- EXTR, EXTRA
- Site
- R107
- Named Organization
- Dept of Engineering + Buildings
- Fcc
- Gj Hopkins
- Johnson Controls
- Va Polytechnic Inst + State Univ
- Ashrae, American Society of Heating, Refrigerating + Air-Conditioning Engineers
- Breakell
- Commonwealth of Va
- Author (Organization)
- Ashrae, American Society of Heating, Refrigerating + Air-Conditioning Engineers
- Hc Yu + Associates
- Va Polytechnic Inst + State Univ
- Named Person
- Broocke, N.I.
- Burnley, H.G.
- Cothran, H.T.
- Davis, A.J.
- Edwards
- Elovitz
- Emerson, E.C.
- Galloway, W.
- Hayward, C.
- Jamerson, W.E.
- Kuykendall, J.G.
- Lawson
- Leroy, P.
- Lilly, J.
- Peroe, R.F.
- Schubert, R.P.
- Shirley, H.G.
- Trueman
- Warren, S.P.
- Wenger, J.D.
- Master ID
- 2021578685/8936
- 2021578685-8936 Period 2 Project Report Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control 920516 to 930831
- 2021578705-8708 Comparative Evaluation of Displacement Ventilation and Conventional Vav Systems for Indoor Air Quality Control
- 2021578709
- 2021578711-8717 Proposal to Philip Morris, Usa for Continuation of Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control
- 2021578719-8753 Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control Status Report: Design Process of the Research and Demonstration Facility Phase II
- 2021578755-8762 Indoor Environment Program Meeting with the Science Advisory Committee 930129 Minutes and Action Items
- 2021578764-8780 Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control Progress Report 920515 - 921115
- 2021578781-8785 Appendix A Abstracts for Indoor Air '93
- 2021578786-8790 Appendix B Project Overview Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control
- 2021578791-8798 Appendix C Performance Criteria
- 2021578800-8815 Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control Progress Report 921116 - 930215
- 2021578816-8824 Appendix A Minutes of the 930129 Science Advisory Committee Meeting
- 2021578825-8831 Appendix B Rational Building Performance and Prescriptive Criteria for Improved Indoor Environmental Quality
- 2021578832-8838 Appendix C Modeling the Thermal and Indoor Air Quality Performance of Vertical Displacement Ventilation Systems
- 2021578839-8845 Appendix D Evaluation of A Vertical Displacement Ventilation System
- 2021578847-8855 Design and Construction of A Facility for Research and Demonstration of Healthy Building Concepts
- 2021578856 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 3. Combustion Products, Risk Assessment, Policies
- 2021578857-8862 Rational Building Performance and Prescriptive Criteria for Improved Indoor Environmental Quality
- 2021578863 Modeling the Thermal and Indoor Air Quality Performance of Vertical Displacement Ventilation Systems
- 2021578864 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 5. Ventilation
- 2021578865-8870 Modeling the Thermal and Indoor Air Quality Performance of Vertical Displacement Ventilation Systems
- 2021578871 Evaluation of A Vertical Displacement Ventilation System
- 2021578872 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 5. Ventilation
- 2021578873-8878 Evaluation of A Vertical Displacement Ventilation System
- 2021578879 A Characterization of Methodologies for Assessing Human Responses to the Indoor Environment
- 2021578880 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 1. Health Effects
- 2021578881-8886 A Characterization of Methodologies for Assessing Human Responses to the Indoor Environment
- 2021578898-8903 Appendix A Specification Section 15995: Commissioning of Hvac System Contract Specifications for Architecture Research and Demonstration Facility Phase II, Virginia Polytechnic Institute and State University, College of Architecture and Urban Studies, Blacksburg Virginia, Rev. 11 930800
- 2021578905 Fluid Filtration: Gas Volume I A Symposium Sponsored by Astm Committee F-21 on Filtration and the American Program Committee of the Filtration Society Philadelphia, Pa, 861020 - 861022
- 2021578906-8926 Filtration As A Method for Air Quality Control in Occupied Spaces
- 2021578927 Indoor Air Volume 5 Buildings, Ventilation and Thermal Climate
- 2021578928-8932
- 2021578934-8936 Economic Modeling of Vav and Vdv Systems in Rdf II
Related Documents:
Document Images
A CASE STUDY: COST IMPLICATIONS FOR HVAC COMMISSIONING
Julie Seelen James E. Woods, P.E. John J. Harmon, P.E.
Member ASHRAE Fellow ASHRAE Life-Member ASHRAE
ABSTRACT
The use of formal commissioning processes for HVAC systems has recently increased
1
in the United States. The prime objective of commissioning is to verify that the HVAC
systems function as intended by the original design. The documentation and operator
training, also included in the commissioning, should result in a better understanding of the
systems and therefore better operation and maintenance practices. This could result in
increased assurance of delivering a healthy building. Although little quantitative evidence
exists, it is generally assumed that this process is cost-effective.
To study its effectiveness, a commissioning process has been instituted' for a small
new research facility. Eight bids were received for this project and'the anticipated cost for the
contractor's participation in the commissioning ranged' from 0% to 2% increase of the base
bid. A follow-up survey with the eight bidders of the project revealed that none of them had'
experience with the commissioning process. The total cost of commissioning including fee for
the commissioning authority was approximately 2.5% of the total project budget.
No identifiable cost avoidances were detected during the construction phase, primarily
due to the owner's inexperience with this process. However, substantial cost avoidance was
realized during acceptance and post-acceptance phase estimated for the first year at 50% of
the commissioning cost. Recommendations are given on additional commitments required
from owner, designers and contractors to realize the potential of the commissioning process.
J. ee en, eseare ssocaa e: J.E. oo .s, .i iam E. amerson r ro essor o ui mg
Construction: Indoor Environment Program, Virginia Polytechnic Institute and State University,
Blacksburg, Virginia; J.J. Harmon, Senior Vice President HC Yu and Associates, Consulting
Engineers, Richmond, Virginia.

INTRODUCTION
The purpose of the commissioning process, as proposed in the guideline from
ASHRAE (ASHRAE 1989, Lawson 1991) is threefold:
1. To verify operation and functional performance of the HVAC systems for compliance
with the design intent.
2. To document the design, the construction requirements including test-inspections,Test
And Balancing reports (TAB), warranties, and as-builts, and to review the operation
and maintenance manuals.
3. To train personnel for operation and maintenance of the HVAC equipment and
systems.
Although most of these procedures are presumed to be included in the responsibilities
of the players in the construction process, they are not always executed. Formalizing these
procedures and adding an overall performance verification maximizes the assurance for the
owner that he will receive an adequately working HVAC system (Elovitz 1992).
The commissioning process typically involves the design engineer, the contractor, the
building owner, and the commissioning authority (CA). However, there is no consensus that
anyone of these participants has a mandate to serve as the commissioning authority (FCC
1992). The design engineer, who is responsible for the design of a HVAC system that meets
the criteria set forth by the owner, may be best equipped to verify system performance
according to design intent but may have a potential conflict of interest. The contractor, who is
responsible for the construction and deliverance of a working system, may be best equipped
to train the personnel in operation and maintenance but may not understand the design intent.
Other possible sources of commissioning authorities include TAB firms, independent
architect/engineering firms, and the building owner.

Although little quantitative evidence exists, it is generally assumed that this process is
cost-effective. The process, when initiated at the pre-design phase, has the potential to detect
areas of conflict in the design and may prevent costiy change orders. During the construction
and acceptance phase the owner will have a better chance of getting a system performing to
meet his requirements without exceeding the budget or time schedule. This has been
demonstrated in several cases in Canada (Trueman 1989). Instituting the commissioning in
Maryland resulted in shorter punch-lists, improvement of the overall quality of the projects,
better training, and no claims or overruns so far (Edwards 1993). The training of operation
and maintenance personnel and the documentation should result in a better understanding of
the systems and therefore better O&M practices. The entire process should result in
increased assurance of delivering and maintaining a healthy building.
This paper reports the findings of a case study where a commissioning process was
Instituted during the pre-design phase of a new research facility. The cost-effectiveness of the
commissioning process is evaluated and recommendations for future specifications are
provided.
THE CASE: A NEW RESEARCH AND DEMONSTRATION FACILITY
The Research and Demonstration Facility (RDF) grew out of the need to investigate
issues related to the evaluation and influence of indoor environment on human responses at
full-scale. The intent of this facility is twofold:
1. To investigate systems that control exposure to four stressors, i.e., thermal, lighting, air
quality and acoustic; and to satisfy criteria which qualify a building to be a healthy
building.
2. To demonstrate innovative building systems.

The primary focus of the initial research is an evaluation and comparison of two HVAC
systems, i.e., variable air volume and vertical displacement, for thermal, air quality and
economic performance.
Because the work that will be done at RDF represents an on-going research agenda
evolving over time, the building must respond as a dynamic and reconfigurable research
laboratory. Therefore, a column-supported space frame with a masonry infill at the perimeter
that allows for the expansion or reconfiguration of the enclosure system was chosen. The
space frame provides an interstitial space which accommodates duct runs, mechanical
equipment, lighting systems, and data communication equipment.
The facility accommodates two large office areas of 700 square feet each, a
conference room (200 sq ft), an instrumentation room (250 sq ft), and a mechanical room
(1240 sq ft). The two offices appear identical but the HVAC systems are different. One office
is served by a conventional VAV system with ceiling supply and a ceiling plenum return. The
other office is served by a vertical displacement system with supply air via a sub-floor plenum
through a perforated' floor/carpet. The return air in this office passes through the grilles in the
ceiling and is ducted back to the air handling unit. A third air handling unit, with 100% outdoor
air, serves the conference room, corridors and instrumentation room. A more detailed
description of this facility was reported in Schubert et al., 1992.
Because the mechanical systems are a critical component of this facility, the
commissioning process was instituted to:
1. Ensure that the systems function according to their design intent.
2. Minimize the delay in start-up time.
3. Evaluate the commissioning process and its cost-effectiveness.
The design engineers of the systems were retained as the commissioning authority.
The others involved are the contractor and his mechanical sub-contractor, the TAB-agency,

the owner, the manufacturer and installer of the Direct Digital Control-system (DDC), and the
research group who is the future user of the facility. The research group also serves as the
evaluator of the procurement process and life cycle cost of the facility. The responsibilities of
the owner, contractor, commissioning authority, and design engineer were outlined in the bid
documents (See appendix A). As the DDC-system was provided under a separate agreement
with the owner, the responsibilities of this co.ntractor were not defined in these bid documents.
Although the design engineer was retained by the owner as the commissioning authority, the
cost for their participation in the commissioning process was negotiated separately from the
cost for design.
COST IMPLICATIONS
Pre-design and Design Phase
During the pre-design phase, the HVAC commissioning parameters and frame-work
were set up. The owner also defined the building program. In the design phase, the
commissioning process was specified and included in the contract documents (Appendix A).
As the contractors likely to bid the project were inexperienced with commissioning, the
process was further explained at the pre-bid meeting. The commissioning plan, detailing the
implementation of the commissioning process and the testing protocol was not part of the
contract documents but was released during the construction phase.
The extra cost for the design engineer to specify the commissioning process and meet
the requirements as specified therein added less than 2% to the overall cost for the
engineering design. The total cost for the commissioning by the design engineer as the
commissioning authority added 14% to the total architect and engineering fees for this small,
(i.e., 1850 sq ft of net occupiable space) complex facility (i.e., research facility with three

independent, different HVAC systems).
A potential cost increase, that did not occur in this project, was the increase due to
changes the design engineer might have been required to make per directions from an
independent commissioning authority.
Construction Phase
Initial construction cost-To obtain information on the cost for the general contractor
to participate in the commissioning process, it was included as an add-alternate item in the bid
documents. Eight bids were received and the add-aitemates ranged from 0% to 2% increase
of the base bid (See Table 1). A follow-up survey was conducted and all contractors and their
sub-contractors were interviewed. None of the eight general contractors had any experience
with the commissioning process. Most general contractors used the quote from the
mechanical subcontractor as the bid-price for the add-aitemate. Some added an additional
administration cost. The bidder, lowest for the base bid and the total bid, reduced the quote
for the commissioning by 22% after the pre-bid' meeting, where some clarifications to the
specifications were made. One bidder felt that commissioning added cost that could be
justified for this facility only because it was a research facility.
Including the commissioning process in the bid documents caused some mechanical
contractors not to bid the project. Most mechanical bidders misunderstood the scope of the
work and were not clear on their liability. Not all bidders attended the pre-bid conference.
One of the mechanical bidders intended to hire an engineering firm as the Commissioning
Authority, although the specifications clearly stated that the owner would engage the CA. ~
N
None of the mechanical bidders had experience with the commissioning process or were 0A
familiar with the ASHRAE GP-1 (ASHRAE 1989). ~
~
m
The actual cost for the genwral contractor to participate in the commissioning was 1.4% N

increase of the base bid price or 6.6% increase of the cost for mechanical and plumbing bid
for this small, complex facility.
Change ordets- More than thirty RFP's (Request For Price) were issued on this
project, one third related to the HVAC systems. According to the owner's representative, this
is not an unusual number of changes for projects like this, but according to the general
contractor this number is high for a project of this cost. Compared to recognizing and
correcting these changes during design the increase of the total construction price due to the
change-orders involving the HVAC systems was estimated at less than 1% of the project base
bid. A goal for the commissioning process should be to eliminate all incremental cost due to
change orders.
Completion on time- Substantial completion was reached six and a half weeks after
the original schedule. Two weeks of the time-delay was weather-related, two weeks delay
was due to miscommunication on start-dates, one week was due to contractor delay. One
and a half weeks was due to change-orders related to the HVAC systems. If these change-
orders would have been prevented, the one and a half weeks time delay would not have
occurred. This was delay in productive occupancy for this facility, a cost that may have been
avoided. Another goal for the commissioning process should be to eliminate all time
extensions to the change orders.
Acceptance Phase and Post-acceptance Phase
During the acceptance phase, the training of operation and maintenance personnel
was carried out in addition to the verification of system installation and functional performance.
The initial training of O&M personnel was done in one day and included three parts. First, the
design engineer explained the intent of the system design. Second, the mechanical sub-
contractor presented the equipment, operation and maintenance requirements. The last part

was a walk-thru of the building. The training on the control system was set for a later date.
Participating O&M personnel were very appreciative of the fact that the design intent of the
systems, explained by the design engineer, was also included in the training session.
The commissioning authority verified the performance of the systems, as outlined in
ASHRAE GP-1, with help of the mechanical contractor. The performance verification of the
waterside of the HVAC systems detected four items that were not functioning correctly, i.e.
three items pertaining to boiler operation and one pertaining to chiller operation. These items
were corrected immediately or during the week following the verification. Correcting these
items before final completion avoided energy and O&M costs that would have occurred due to
inappropriate capacity control. The performance verification of the airside of HVAC systems
detected these malfunctions: one pertaining to draining and condensate pans, one pertaining
to problems with air balance, and one pertaining to problems with control stability. Without
commissioning, these problems may not have appeared for several months of operation and
would have resulted in avoidable O&M costs to investigate and avoidable loss of productive
research time. As the HVAC systems are the subject of research in this facility, the use of the
commissioning process to assure that the systems are working per design intent at final
completion also assures that the research can start immediately after final completion, and
save valuable start-up time.
CONCLUSIONS AND RECOMMENDATIONS
The total cost for commissioning, including cost for the commissioning authority and ~y
~
the cost for the contractor to participate in the commissioning process, was approximately ~
2.5% of the total project budget of this small, complex project. Because of the small complex ~
~
scale of this project, we conclude that the 2.5% cost may be considered a limit and that larger ~
~

projects of similar or less complexity can be commissioned for a smaller percentage of total
project budget.
No identifiable cost avoidances were detected during the construction phase, primarily
due to the owner's inexperience with this process. However, it is anticipated that cost
avoidances during construction will be realized by the owners on subsequent projects by
continuing to use the commissioning process.
Substantial cost avoidance was realized during the acceptance phase and post-
acceptance phase by:
1. Assuring that design intent was met at time of final completion assuring that the
research agenda could be initiated.
2. Preventing energy waste due to detection of inappropriate capacity control of boiler
and chiller.
3. Preventing unnecessary on-site visits by O&M personnel to trouble shoot the system.
4. Reducing unnecessary loss of productive research time due to system malfunctions.
We therefore conclude from an analysis of the projected cost that the cost avoidance accrued
during the first year will amount to approximately 50%a of the commissioning cost.
This case study provides strong evidence that the commissioning process can be cost-
effective. However, to realize its potential, additional commitments are required from the
owner, designers and contractors:
1. Although in this case study, the bid documents clearly defined the roles and
responsibilities, several bidders misunderstood the scope of the work. Therefore, the
bid documents should not only define the roles and responsibilities of the different
participants, but also include the commissioning plan in order to give the bidders a
better idea of expectations and the work effort involved.
2. Attending the pre-bid meeting should be mandatory, and should include a

discussionlexplanation of the commissioning process.
3. At the pre-construction meeting a cpm-schedule (critical path method) for construction
and commissioning should be agreed upon.
4. All parties to the commissioning process must be present during the final verification
and training periods.
ACKNOWLEDGEMENTS
We recognize and thank the following people and organizations: H.G. Bumley, Jr. and C.
Hayward of Philip Morris USA; J. D. Wenger and E. C. Emerson of Johnson Controls; A. J.
Davis, architect of record, and W. Galloway and R.P. Schubert for assisting in the design
process (College of Architecture and Urban Studies); J. G. Kuykendall and S. P. Warren of
Facilities Planning and Construction at Virginia Tech; N. I. Broocke, H. G. Shirley, and R. F.
Peroe for their cooperation in the Department of Engineering and Buildings (Commonwealth of
Virginia); P. LeRoy and J. Lilly of Breakell Inc., and H. T. Cothran of G. J. Hopkins, Inc., and
all other contractors who participated in the construction andlor follow-up study.
REFERENCES
ASHRAE. 1989. ASHRAE Guideline 1-1989, Guideline for Commissioning of HVAC Systems.
Atlanta: American Society of Heating, Refrigerating, and Air-Conditioning Engineers, Inc.
Edwards F. C. 1993. Integration of commissioning into construction quality control program.
Seminar Presentation at ASHRAE Winter Meeting in Chicago, 1993.
Elovitz, K.M. 1992. Commissioning building mechanical systems. ASHRAE Transactions.
Vol. 98, Part 2, pp.543-552.
FCC: Federal Construction Council. 1992. Commissioning mechanical and electrical systems
in buildings (Summary of a symposium). Technical Report No. 114. Washington D.C.:
Building Research Board of the National Research Council.
Lawson, C. N. 1991. Documentation of the commissioning process. ASHRAE Transactions,.
Vol. 97, Part 1, pp.765-772.
Schubert, R. P.; J. Seelen; J. E. Woods; and S. Arora. 1992. Design and construction of a
facility for research and demonstration of healthy building concepts. Proceedings of the AIA
Symposium: Designing for Healthy Buildings. Los Angeles, November, 1992.
Trueman, C. S. 1989. Commissioning: An owner's approach for effective operations.
ASHRAE Transactions, Vol. 95, Part 1, pp.895-899.
