Philip Morris
Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control Progress Report 921116 - 930215
Fields
- Type
- REPT, REPORT, OTHER
- CHAR, CHART, GRAPH, TABLE, MAPS
- DRAW, DRAWING
- CHAR, CHART, GRAPH, TABLE, MAPS
- Area
- CENTRAL FILES/PRE-DB WAREHOUSE
- Site
- R107
- Named Person
- Davis, J.
- Leroy, P.
- Lowder, D.
- Seelen, J.
- Warren, S.
- Leroy, P.
- Named Organization
- Ashrae, American Society of Heating, Refrigerating + Air-Conditioning Engineers
- Breakell
- Indoor Air 93
- Johnson Controls
- Qa Qc Team
- Science Advisory Comm
- Va Tech
- 6th Intl Conf Indoor Air Quality Climate
- Breakell
- Recipient (Organization)
- PM, Philip Morris
- Document File
- 2021578674/2021578937/Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control
- Litigation
- Ppla/Produced
- Author (Organization)
- Va Tech
- Master ID
- 2021578685/8936
Related Documents:- 2021578685-8936 Period 2 Project Report Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control 920516 to 930831
- 2021578705-8708 Comparative Evaluation of Displacement Ventilation and Conventional Vav Systems for Indoor Air Quality Control
- 2021578709
- 2021578711-8717 Proposal to Philip Morris, Usa for Continuation of Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control
- 2021578719-8753 Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control Status Report: Design Process of the Research and Demonstration Facility Phase II
- 2021578755-8762 Indoor Environment Program Meeting with the Science Advisory Committee 930129 Minutes and Action Items
- 2021578764-8780 Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control Progress Report 920515 - 921115
- 2021578781-8785 Appendix A Abstracts for Indoor Air '93
- 2021578786-8790 Appendix B Project Overview Evaluation of Displacement Ventilation and Conventional Variable Air Volume Systems for Indoor Air Quality Control
- 2021578791-8798 Appendix C Performance Criteria
- 2021578816-8824 Appendix A Minutes of the 930129 Science Advisory Committee Meeting
- 2021578825-8831 Appendix B Rational Building Performance and Prescriptive Criteria for Improved Indoor Environmental Quality
- 2021578832-8838 Appendix C Modeling the Thermal and Indoor Air Quality Performance of Vertical Displacement Ventilation Systems
- 2021578839-8845 Appendix D Evaluation of A Vertical Displacement Ventilation System
- 2021578847-8855 Design and Construction of A Facility for Research and Demonstration of Healthy Building Concepts
- 2021578856 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 3. Combustion Products, Risk Assessment, Policies
- 2021578857-8862 Rational Building Performance and Prescriptive Criteria for Improved Indoor Environmental Quality
- 2021578863 Modeling the Thermal and Indoor Air Quality Performance of Vertical Displacement Ventilation Systems
- 2021578864 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 5. Ventilation
- 2021578865-8870 Modeling the Thermal and Indoor Air Quality Performance of Vertical Displacement Ventilation Systems
- 2021578871 Evaluation of A Vertical Displacement Ventilation System
- 2021578872 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 5. Ventilation
- 2021578873-8878 Evaluation of A Vertical Displacement Ventilation System
- 2021578879 A Characterization of Methodologies for Assessing Human Responses to the Indoor Environment
- 2021578880 Indoor Air '93 Proceedings of the 6th International Conference on Indoor Air Quality and Climate Volume 1. Health Effects
- 2021578881-8886 A Characterization of Methodologies for Assessing Human Responses to the Indoor Environment
- 2021578887-8897 A Case Study: Cost Implications for Hvac Commissioning
- 2021578898-8903 Appendix A Specification Section 15995: Commissioning of Hvac System Contract Specifications for Architecture Research and Demonstration Facility Phase II, Virginia Polytechnic Institute and State University, College of Architecture and Urban Studies, Blacksburg Virginia, Rev. 11 930800
- 2021578905 Fluid Filtration: Gas Volume I A Symposium Sponsored by Astm Committee F-21 on Filtration and the American Program Committee of the Filtration Society Philadelphia, Pa, 861020 - 861022
- 2021578906-8926 Filtration As A Method for Air Quality Control in Occupied Spaces
- 2021578927 Indoor Air Volume 5 Buildings, Ventilation and Thermal Climate
- 2021578928-8932
- 2021578934-8936 Economic Modeling of Vav and Vdv Systems in Rdf II
- Characteristic
- EXTR, EXTRA
- Date Loaded
- 07 Jan 1999
- UCSF Legacy ID
- ikc33e00
Document Images
EVALUATION OF
DISPLACEMENT VENTILATION AND CONVENTIONAL VARIABLE AIR
VOLUME SYSTEMS FOR INDOOR AIR QUALITY CONTROL
PROGRESS REPORT
November 16, 1992 - February 15, 1993
for
Philip Morris USA
March 4, 1993
~
~
Indoor Environment Program N
OA
College of Architecture and Urban Studies
~
Virginia Tech, Blacksburg ~
~.
O

TABLE OF CONTENTS
TABLE OF CONTENTS
INTRODUCTION ...............
i
1=
GENERAL TASKS .................................. 2
TASK 1 CONSTRUCTION OF RDF II ............ 2
TASK 3 PROGRESS REPORTS ................ 5
TASK 4 PUBLICATIONS ...................... 5
PHYSICAL SYSTEMS TASKS .......................... 6
TASK 1 PROTOCOL DEVELOPMENT ............... . ... . . . . 6
TASK 2 DEVELOPMENT OF PERFORMANCE CRITERIA ......... 6
TASK 3 MODELING OF SYSTEMS ......................... 6
TASK 4 QUALITY ASSURANCE AND QUALITY CONTROL ........ 7
TASK 5 DATABASE DEVELOPMENT ........................ 11
TASK 6 TESTING AT RICHMOND .......................... 12
TASK 7 ACQUISITION AND DEVELOPMENT OF
INSTRUMENTATION ................... ........
12
TABLE 1 Measurements and Instrumentation ................... 13
APPENDIX A
APPENDIX B
APPENDIX C Minutes of the January 29, 1993 Science Advisory
Committee Meeting ..............................
Rational Building Performance and Prescriptive Criteria for
Improved Indoor Environmental Quality ................
Modeling the Thermal and Indoor Air Quality Performance
of Vertical Displacement Ventilation Systems ..........
Al
Bi
C1
APPENDIX D Evaluation of a Vertical Displacement Ventilation System ... D1
i

LIST OF FIGURES
Figure 1 Duct work and access parts for the HVAC system ......... 4

Pro9ram Report Evaluation of Ventilation Systems
February 15, 1993
INTRODUCTION
During the period from November 15, 1992 to February 15, 1993, construction of
Phase II of the Research and Demonstration Facility (RDF II) was 80% completed.
The mechanical systems are now being installed. Development of the modeling of the
systems has further progressed and papers on the performance criteria and the model
methodology have been submitted to an International Conference. During this period
tests were also carried out at the test facility of Philip Morris' Research Center in
Richmond. A paper presenting the results from these tests has also been submitted.
Data obtained from these tests have also been used to verify the proposed model.
Experience from these tests and extensive use of the instrumentation will enabled
development of a detailed protocol and quality assurance procedures.
This progress report follows the tasks outlined in the proposal (submitted 9 October).
The work accomplished within each task and the activities planned for the next period
have been described. Papers written during this period are included in the
appendices, and are referred to in this report whenever progress under specific tasks
is aptly described therein.

Progress Report Evaluation of Ventilation Systems
February 15, 1993
GENERAL TASKS
TASK 1 CONSTRUCTION OF RDF II
On November 19, 1992, a meeting was held to discuss the constnuction schedule,
prepared using the Critical Path Method: Participating in the meeting were Danny
Lowder (PM), Julie Seelen (IEP), Paul LeRoy (Breakell), Steve Warren (VA Tech), and
Jack Davis (VA Tech). The proposed schedule already reflected a time extension of
two weeks, which was granted to the contractor because the date of the Notice to
Proceed and the start date were too close, as discussed in the previous progress
report. The anticipated date of substantial completion is March 9, 1993. The
approach to construction was to place the roof as early as possible and make the
building watertight. This would enable activitities to proceed inside during most of the
winter, e.g. pouring the slab on grade. All participants at the meeting agreed that the
key to completing the project on schedule are favorable weather, timely approval of
shop-drawings, and timely acquisition of owner furnished products. The contractor
has a submittal log for all shop drawings depicting dates by which approval should be
obtained so as not to impact the schedule. The contractor also notifies the owner of
critical dates.
The weather in November and December was not very favorable for construction and
the lifting and placement of the space frame into position was delayed by three weeks.
The weather in January was cooperative and working with double crews brought
construction back on schedule. At this time, the building is watertight and dry-in is
expected by the third week of February. All submittals have been approved and most
materials and equipment have been received. Owner furnished items are on order.
Coordination with Johnson Controls, who donated the DDC-system, has not incurred
any problems to date.
General Tasks 2

Progres. Report Evaluation of Ventilation Systans
Febnuary 15, 1993
Two change-orders have been issued so far, adding three percent to the cost of
construction. The main expense was incurred in the removal and replacement of the
existing eiectrical- duct-bank, which was located under Phase II and serves Phase I of
the building. A cost credit for rock excavation is expected since the amount of rock
encountered was less than that estimated in the contract documents.
A pre-commissioning meeting was held January 14, 1993. Participating in this
meeting were the contractor, the mechanical and electrical sub-contractors, a
representative from Johnson Controls, the engineer, the architect, the owner, and the
research team. In this meeting the commissioning procedures were discussed and
several issues concerning the mechanical equipment were clarified. One of these
issues was the spiral duct work. This duct work is insulated inside and insulation and
air flow are separated either by a solid metal lining or a perforated metal lining.
Locations where the duct should have solid lining versus the perforated lining were
also discussed. It was decided that the duct work for the conventional system should
be internally lined as it represents conventional designs in other office buildings. The
part of the vertical displacement system that is the same as the conventional system
has the same lining as the conventional system, i.e. the return air duct from the room
to the air handling unit (0-700 cfm) is perforated', whereas the return air duct from the
room (900-1600 cfm) to the fan powered box is solid (see Figure 1). Also, the supply
air duct below the flooring has internal lining. Eleven locations for access ports in the
ducts have been identified to enable periodic checking of the insulation and interior of
the duct work.
General Tasks 3

s
Al1 HAMOU/G UMi 1
.W
AR HMfbtllG IIII 3
rW
Figure 1. Duct work and access ports for the HVAC systems.
9100CM94sIzOz

Progres. Report Evaluation of Ventiiation Systaes
Febnjary 15, 1993
TASK 2 SCIENCE ADVISORY COMMITTEE MEETINGS
The Science Advisory Committee met on January 29, 1993. The minutes are included
in Appendix A. The next meeting is planned for November 11-12, 1993 in Blacksburg.
An informal meeting may take place at the ASHRAE meeting in June 1993 in Denver.
TASK 3 PROGRESS REPORTS
The next progress report, due 15 March 1993, will include a status report on the
construction of RDF Phase II, the results of additional tests in the chamber at
Richmond, and baseline data on the two test rooms in RDF.
TASK 4 PUBLICATIONS
The following papers (Appendices B, C, and D) were submitted for Indoor Air '93, the
6'h International Conference on Indoor Air Quality and Climate:
Modeling the Thermal and Indoor Air Quality Performance of Vertical
Displacement Ventilation Systems
Evaluation of a Vertical Displacement Ventilation System
Rational Building Performance and Prescriptive Criteria for Improved Indoor
Environmental Quality

Progns Report Evaluation of Ventilation Systems
Febraary 15, ,1993
PHYSICAL SYSTEMS TASKS
TASK 1 PROTOCOL DEVELOPMENT
The protocol for the testing done at the test chamber in Richmond is briefly described
in a paper (Appendix D) for Indoor Air'93. Experience from these tests will be the
basis for a detailed protocol for the measurements in the Research and Demonstration
Facility.
TASK 2 DEVELOPMENT OF PERFORMANCE CRITERIA
A paper is enclosed in Appendix B.
The concept described in the paper will be further developed and reviewed by the
Science Advisory Committee.
TASK 3 MODELING OF SYSTEMS
A paper is enclosed in Appendix C.
The effect of the wall boundary on the air flow and air quality is presently being
studied. Methods of representing the wall effects will be investigated. The model will
now be used to predict the parameters for the test room in RDF II.
Physica! Systems Tasks

?royre.s Report Evaluation of Ventilation Systems
February 15 1993
TASK 4 QUALITY ASSURANCE AND QUALITY CONTROL
4.1 QA Objectives
The objective of the Quality Control/Quality Assurance (QA/QC) program is to
guarantee the integrity of the measurement data that is being taken in support of the
research protocol. Integrity can be further defined in terms of precision, accuracy,
completeness, representativeness and comparability. These terms are defined as:
Accuracy - the degree of agreement of a measurement (or an average of
measurements of the same thing), X, with an accepted reference or true value, T
usually expressed as the difference between the two values, X-T, or the difference as
a percentage of the reference or true value, 100 (X-T)IT, and sometimes expressed as
a ratio, )UT. Accuracy is a measure of the bias of the system.
Precision - a measure of mutual agreement among individual measurements of
the same property, usually under prescribed similar conditions. Precision is best
expressed in terms of the standard deviation.
Completeness - a measure of the amount of valid data obtained from a
measurement system compared to the amount that was expected to be obtained
under correct normal conditions. Completeness is best expressed as a percentage.
Representativeness - expresses the degree to which data accurately and
precisely represents a characteristic of a population, parameter variations at a
sampling point, a process condition, or an environmental condition.
Representativeness is best expressed as a percentage.
Physical'Systems Tasks 7
